INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Minor sidewalk repairs and roadway work will commence when winter moratorium lifted in anticipation of final paving. Final paving, striping, and signal activation tentatively scheduled for May 2024.
  • Arthur Street: Minor sidewalk repairs and roadway work will commence when winter moratorium lifted in anticipation of signal activation. Signal Activation tentatively scheduled for April 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete in mid-April. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur in April and completed by early May. Temporary barriers to be installed along north side of roadway to protect incomplete construction sites. Gas line installation from Arthur Street to Building A is complete.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work complete other than punch list items. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing, anticipated to be complete by end of April. Residential and base building substantial completion anticipated for April 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.