INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of roadway work complete. Sidewalk repairs on-going with two-way traffic and pedestrian access continuing to be maintained.
  • Arthur Street: no roadway work is scheduled within Arthur Street this week. Top course pavement anticipated for mid-September.

Future Guest Street Extension

  • Construction of Guest Street is ongoing, with contractor installing cement concrete sidewalks, boundary monuments, and base materials for bike path and pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906