September 25, 2023 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Working on preparing roadway for final paving which is anticipated for mid-late October Preparation includes raising structures and preparing pavement transitions. Private utility (National Grid and Eversource) work is occurring within Everett and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: Top course pavement scheduled for the night of Thursday October 5th. Activity this week will include work required for preparation of top course paving, including raising structures, installing message boards, and patching binder course pavement.

Future Guest Street Extension

  • Construction of the hardscape area on the south side of Guest Street is progressing, including installation of the bike lane, pavers, and concrete sidewalks. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

September 18, 2023 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street:Majority of roadway work complete. Concrete patching in sidewalk occurring this week. Private utility (National Grid and Eversource) work will be occurring within Everett and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: Top course pavement scheduled for the night of Monday October 2nd. Activity this week will include work required for preparation of top course paving, including raising structures, installing message boards, and patching binder course pavement.

Future Guest Street Extension

  • Construction will commence in full of the hardscape area on the south side of Guest Street, including the bike lane, pavers, and sidewalk areas. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

September 11, 2023 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Majority of roadway work complete. Concrete patching in sidewalk occurring this week. Private utility (National Grid and Eversource) work will be occurring within Everett and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: no roadway work is scheduled within Arthur Street this week. Top course pavement anticipated for mid-September.

Future Guest Street Extension

  • Construction of Guest Street will be sporadic this week with only minor improvements occurring, including installing cement concrete sidewalks, boundary monuments, and base materials for bike path and pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

September 4, 2023 – Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Majority of roadway work complete. No work anticipated this week. Private utility (National Grid and Eversource) work will be occurring within Everett and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: no roadway work is scheduled within Arthur Street this week. Top course pavement anticipated for mid-September.

Future Guest Street Extension

  • Construction of Guest Street will be sporadic this week with only minor improvements occurring, including installing cement concrete sidewalks, boundary monuments, and base materials for bike path and pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

August 28, 2023 Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of roadway work complete. Sidewalk repairs on-going with two-way traffic and pedestrian access continuing to be maintained.
  • Arthur Street: no roadway work is scheduled within Arthur Street this week. Top course pavement anticipated for mid-September.

Future Guest Street Extension

  • Construction of Guest Street is ongoing, with contractor installing cement concrete sidewalks, boundary monuments, and base materials for bike path and pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

August 21, 2023 Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Street Reconstructions

  • Everett Street Intersection: construction is ongoing in Everett Street and includes the installation of curb and sidewalk. Two-way traffic and pedestrian access will be maintained throughout this week.
  • Arthur Street: no roadway work is scheduled within Arthur Street this week. Top course pavement anticipated for mid-September.

Future Guest Street

  • Construction of Guest Street is ongoing, with contractor installing vertical granite curbing, concrete sidewalks, permeable under drains, and lighting infrastructure this week. Pedestrian access from the parking areas to Stop & Shop will be maintained.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

August 14, 2023 Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Street Reconstructions

  • Everett Street Intersection: construction is ongoing in Everett Street and includes the installation of curb and sidewalk. Two-way traffic and pedestrian access will be maintained throughout this week.
  • Arthur Street: no roadway work is scheduled within Arthur Street this week

Future Guest Street

  • Construction of Guest Street is ongoing, with contractor installing vertical granite curbing, concrete sidewalks, permeable under drains, and lighting infrastructure this week. Pedestrian access from the parking areas to Stop & Shop will be maintained.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

July 2023 Construction Update

 

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Street Reconstructions

  • Everett Street Intersection: construction is ongoing in Everett Street and includes the installation of curb and sidewalk. Two-way traffic and pedestrian access will be maintained throughout this week.
  • Arthur Street: no roadway work is scheduled within Arthur Street this week

Future Guest Street

  • Future Guest Street Extension: construction of Guest Street Extension is underway. Binder course pavement has been installed and the contractor will be installing vertical granite curbing, lighting infrastructure, permeable under drains, and concrete sidewalks this week. Pedestrian access from the parking areas to Stop & Shop will be maintained.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

July 2022 Construction Updates

INFRASTRUCTURE – new street grid: Guest Street extension, Arthur Street extension, Braintree Street extension, and improved Everett Street intersection)

Enabling – to pave the way for construction of future roadways

  • Making final connection to existing water infrastructure at intersection of Braintree Street and Old Everett Street
  • Overall site cleanup and construction signage installation

Homegoods Demolition – to pave the way for construction of Building B

  • Active building demolition complete
  • Site clean-up ongoing
  • Stop & Shop building improvement and minor utility work happening in this area
  • Gravel pad to be utilized for Building A contractor parking

Roadway Phase A – Everett Street intersection and Arthur Street extension improvements

  • Everett Street intersection
    • Installing traffic management devices on Everett and Old Everett Streets restricting traffic to northbound only
    • Pedestrian and bicyclist access to and from Stop & Shop via Everett Street closed beginning July 27th until further notice. Stop & Shop to continue to remain open. Pedestrian and bicyclist to detour to North Beacon and Arthur Street for Stop & Shop access.
    • Installing stormwater structures/infrastructure
    • Demolishing and removing existing retaining wall
    • Installing foundation and precast retaining wall
  • Arthur Street extension
    • Installing site lighting and traffic conduit
    • Additional stormwater work at Hichborn intersection
    • Ordering and installing proposed curbing

BUILDING A – Residential Building with new Stop & Shop grocery store

  • Parking lot demolition, support of excavation and soil removal 100% complete
  • Lower garage level (Level -2) concrete slab 100% complete
  • Upper garage level (Level -1) concrete formwork ongoing
  • Concrete superstructure (2 underground + 2 above ground) forecast to complete Fall 2022
  • Wood framing superstructure (Levels 3 to 6) forecast to complete Spring 2023
  • Overall project completion forecast to complete Early 2024

BUILDING B – Lab/Office Building

  • Exploratory borings complete
  • Mobilization anticipated for 10/22