June 25, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 7/31/24.
  • Arthur Street: All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 7/31/24

Future Guest Street Extension

  • All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 7/31/24. North side roadway improvements will coincide with adjacent development projects.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Temporary occupancy permit obtained. Residential tenant move in’s have begun and will continue to increase through the summer. Stop and Shop opened Friday, June 21st.

COMMUNITY GREEN

    • Construction on the Community Green open space has begun. Early work consists of demolition, drainage installation, and earthwork. Plantings are scheduled for early fall of 2024 with an anticipated completion date by year end.

June 17, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Signal activation occurred May 13th, final paving occurred June 3rd. Final striping of the intersection is scheduled for the week of 6/10. Two way traffic will be maintained during striping, however standard lane closures may impact traffic flow.
  • Arthur Street: All paving, striping and signal activation complete.

Future Guest Street Extension

  • Roadway and sidewalks were opened to public on May 13th, 2024. Majority of roadway and sidewalk work is complete. Minor punch list work remaining in sidewalk and paver areas. Installation of bike racks, benches, and trash receptacles to be complete week of June 10th. Final striping of the roadway is scheduled for the week of 6/10. Two way traffic will be maintained during striping, however standard lane closures may impact traffic flow.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Substantial completion has been achieved and an occupancy permit has been granted Minor work still on-going with an anticipated final completion by mid-summer. Residential tenant move in’s have begun and will continue to increase through the summer. Stop and Shop opening scheduled for Friday, June 21st.

COMMUNITY GREEN

    • Construction on the Community Green open space has begun. Early work consists of demolition, drainage installation, and earthwork. Plantings are scheduled for early fall of 2024 with an anticipated completion date by year end.

June 10, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Signal activation occurred May 13th, final paving occurred June 3rd. Final striping of the intersection is scheduled for the week of 6/10. Two way traffic will be maintained during striping, however standard lane closures may impact traffic flow.
  • Arthur Street: All paving, striping and signal activation complete.

Future Guest Street Extension

  • Roadway and sidewalks were opened to public on May 13th, 2024. Majority of roadway and sidewalk work is complete. Minor punch list work remaining in sidewalk and paver areas. Installation of bike racks, benches, and trash receptacles to be complete week of June 10th. Final striping of the roadway is scheduled for the week of 6/10. Two way traffic will be maintained during striping, however standard lane closures may impact traffic flow.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Substantial completion has been achieved and an occupancy permit has been granted Minor work still on-going with an anticipated final completion by mid-summer. Residential tenant move in’s have begun and will continue to increase through the summer. Stop and Shop opening scheduled for mid-June.

COMMUNITY GREEN

    • Construction on the Community Green open space has begun. Early work consists of demolition, drainage installation, and earthwork. Plantings are scheduled for early fall of 2024 with an anticipated completion date by year end.

May 20, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Signal activation occurred May 13th, and the intersection is now fully operational. Minor utility structure work will occur the week of May 20th and early the week of May 28th. Final paving, is scheduled for Monday June 3rd, with striping to follow soon thereafter. Please note that detours (primarily restricting northbound traffic on Everett) will be in place on June 3rd to accommodate the paving work.
  • Arthur Street: All paving, striping and signal activation complete.

Future Guest Street Extension

  • Roadway and sidewalks were opened to public on May 13th, 2024. Majority of roadway and sidewalk work is complete. Minor punch list work remaining in sidewalk and paver areas. Minor utility structure work will occur the week of May 20th and early the week of May 28th. Final paving is scheduled for Friday May 31st, with striping to follow soon thereafter. Please note that access on Guest Street may be limited to local traffic only on May 31st to accommodate the paving work. Temporary barriers have been installed along north side of roadway to protect incomplete construction sites. Gas line installation from Arthur Street to Building A is complete.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Substantial completion has been achieved and an occupancy permit has been granted Minor work still on-going with an anticipated final completion by mid-summer. Residential tenant move in scheduled for late May. Stop and Shop opening scheduled for mid-June.

COMMUNITY GREEN

    • Construction on the Community Green open space has begun. Early work consists of demolition, drainage installation, and earthwork. Plantings are scheduled for early fall of 2024 with an anticipated completion date by year end.

May 6, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Minor sidewalk repairs and roadway work ongoing in anticipation of final paving. Final paving, striping, and signal activation tentatively scheduled for week of May 28th, 2024.
  • Arthur Street: All paving, striping and signal activation complete.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete early May. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to be completed by mid-May. Roadway opening tentatively scheduled for May 10th 2024. Temporary barriers have been installed along north side of roadway to protect incomplete construction sites. Gas line installation from Arthur Street to Building A is complete.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work complete other than punch list items. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing, anticipated to be complete by end of April/early May. Residential and base building substantial completion anticipated for early May 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.

April 29, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Minor sidewalk repairs and roadway work ongoing in anticipation of final paving. Signal activation tentatively scheduled for May 3rd, 2024. Final paving, striping, and signal activation tentatively scheduled for week of May 28th, 2024.
  • Arthur Street: All paving, striping and signal activation complete.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete early May. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to be completed by mid-May. Roadway opening tentatively scheduled for May 3rd 2024. Temporary barriers have been installed along north side of roadway to protect incomplete construction sites. Gas line installation from Arthur Street to Building A is complete.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work complete other than punch list items. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing, anticipated to be complete by end of April/early May. Residential and base building substantial completion anticipated for early May 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.

April 22, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Minor sidewalk repairs and roadway work ongoing in anticipation of final paving. Signal activation tentatively scheduled for May 1st, 2024. Final paving, striping, and signal activation tentatively scheduled for week of May 28th, 2024.
  • Arthur Street: Minor sidewalk repairs and roadway work ongoing in anticipation of signal activation. Signal Activation tentatively scheduled for week of May 1st, 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete late-April. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to be completed by early May. Roadway opening tentatively scheduled for May 2nd 2024. Temporary barriers have been installed along north side of roadway to protect incomplete construction sites. Gas line installation from Arthur Street to Building A is complete.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work complete other than punch list items. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing, anticipated to be complete by end of April/early May. Residential and base building substantial completion anticipated for early May 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.

April 14, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Minor sidewalk repairs and roadway work ongoing in anticipation of final paving. Final paving, striping, and signal activation tentatively scheduled for week of May 13th 2024.
  • Arthur Street: Minor sidewalk repairs and roadway work ongoing in anticipation of signal activation. Signal Activation tentatively scheduled for week of April 29th 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete late-April. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to be completed by early May. Temporary barriers have been installed along north side of roadway to protect incomplete construction sites. Gas line installation from Arthur Street to Building A is complete.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work complete other than punch list items. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing, anticipated to be complete by end of April/early May. Residential and base building substantial completion anticipated for early May 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.

April 1, 2024 – Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Minor sidewalk repairs and roadway work will commence when winter moratorium lifted in anticipation of final paving. Final paving, striping, and signal activation tentatively scheduled for May 2024.
  • Arthur Street: Minor sidewalk repairs and roadway work will commence when winter moratorium lifted in anticipation of signal activation. Signal Activation tentatively scheduled for April 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete in mid-April. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur in April and completed by early May. Temporary barriers to be installed along north side of roadway to protect incomplete construction sites. Gas line installation from Arthur Street to Building A is complete.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work complete other than punch list items. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing, anticipated to be complete by end of April. Residential and base building substantial completion anticipated for April 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.

February 26, 2024 – Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of work complete for the season. Final paving, striping, and signal activation tentatively scheduled for May 2024.
  • Arthur Street: Majority of work complete for the season. Signal Activation tentatively scheduled for April 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete in March. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur immediately thereafter (late March). Gas line installation from Arthur Street to Building A has begun and is expected to be complete mid-late March.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work ongoing on south side of building. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing. Residential and base building substantial completion anticipated for Spring 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.