April 1, 2024 – Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Minor sidewalk repairs and roadway work will commence when winter moratorium lifted in anticipation of final paving. Final paving, striping, and signal activation tentatively scheduled for May 2024.
  • Arthur Street: Minor sidewalk repairs and roadway work will commence when winter moratorium lifted in anticipation of signal activation. Signal Activation tentatively scheduled for April 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete in mid-April. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur in April and completed by early May. Temporary barriers to be installed along north side of roadway to protect incomplete construction sites. Gas line installation from Arthur Street to Building A is complete.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work complete other than punch list items. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing, anticipated to be complete by end of April. Residential and base building substantial completion anticipated for April 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.

February 26, 2024 – Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of work complete for the season. Final paving, striping, and signal activation tentatively scheduled for May 2024.
  • Arthur Street: Majority of work complete for the season. Signal Activation tentatively scheduled for April 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete in March. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur immediately thereafter (late March). Gas line installation from Arthur Street to Building A has begun and is expected to be complete mid-late March.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work ongoing on south side of building. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing. Residential and base building substantial completion anticipated for Spring 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.

February 12, 2024 – Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of work complete for the season. Final paving, striping, and signal activation tentatively scheduled for May 2024.
  • Arthur Street: Majority of work complete for the season. Signal Activation tentatively scheduled for April 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete in March. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur immediately thereafter (late March). Gas line installation from Arthur Street to Building A expected to begin the week of February 20th and finishing in mid-late March.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work ongoing on south side of building. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing. Project substantial completion anticipated for Spring 2024.

January 29, 2024 – Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of work complete for the season. Final paving, striping, and signal activation to occur in the Spring.
  • Arthur Street: Majority of work complete for the season. Signal Activation to occur late Winter/early Spring.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation to begin January 5th and extend through February. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur early Spring. Gas line installation from Arthur Street to Building A expected to occur between early February to early March.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work ongoing on south side of building. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing. Project completion anticipated for Spring 2024.

January, 9 2024 – Construction Update

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of work complete for the season. Final paving, striping, and signal activation to occur in the Spring.
  • Arthur Street: Majority of work complete for the season. Signal Activation to occur late Winter/early Spring.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation to begin January 5th and extend through February. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur early Spring.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work ongoing on south side of building. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing. Project completion anticipated for Spring 2024.

December 5, 2023 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Installing signage within sidewalk areas and mast arms, and installing signal wiring between Guest and North Beacon Street. Final paving will not occur until the Spring to accommodate the National Grid work occurring in Everett, Old Everett, and Braintree Streets, which is separate from the Allston Yards project.
  • Arthur Street: Top course pavement completed on October 17th. Pavement striping completed 10/26. Installing signage within sidewalk areas and mast arms. Activation of signal infrastructure to occur mid-late December.

Future Guest Street Extension

  • Construction of the hardscape area on the south side of Guest Street is progressing, including installation of the bike lane, pavers, and concrete sidewalks. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

November 13, 2023 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Working on preparing roadway for winter which includes transitioning pavement and applying temporary striping. Final paving will not occur until the Spring to accommodate the National Grid work occurring in Everett, Old Everett, and Braintree Streets, which is separate from the Allston Yards project.
  • Arthur Street: Top course pavement completed on October 17th. Pavement striping completed 10/26. Signage installation and minor temporary improvements will be on-going through early November.

Future Guest Street Extension

  • Construction of the hardscape area on the south side of Guest Street is progressing, including installation of the bike lane, pavers, and concrete sidewalks. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

November 6, 2023 Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Working on preparing roadway for final paving which is anticipated for mid November. Preparation includes raising structures and preparing pavement transitions. National Grid work is occurring within Everett, Old Everett, and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: Top course pavement completed on October 17th. Pavement striping completed 10/26. Signage installation and minor temporary improvements will be on-going through early November.

Future Guest Street Extension

  • Construction of the hardscape area on the south side of Guest Street is progressing, including installation of the bike lane, pavers, and concrete sidewalks. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

October 30, 2023 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Working on preparing roadway for final paving which is anticipated for early November. Preparation includes raising structures and preparing pavement transitions. National Grid work is occurring within Everett, Old Everett, and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: Top course pavement completed on October 17th. Pavement striping completed 10/26. Signage installation and minor temporary improvements will be on-going through early November.

Future Guest Street Extension

  • Construction of the hardscape area on the south side of Guest Street is progressing, including installation of the bike lane, pavers, and concrete sidewalks. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906

October 23 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Working on preparing roadway for final paving which is anticipated for early November. Preparation includes raising structures and preparing pavement transitions. National Grid work is occurring within Everett, Old Everett, and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: Top course pavement completed on October 17th. Striping installation and traffic signal work will occur this week, both requiring work within the roadway, but not roadway shutdowns.

Future Guest Street Extension

  • Construction of the hardscape area on the south side of Guest Street is progressing, including installation of the bike lane, pavers, and concrete sidewalks. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906