INFRASTRUCTURE (Roadway and Utility Work)
Everett and Arthur Reconstructions
- Everett Street Intersection: All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 1/1/25.
- Arthur Street: All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 1/1/25.
Future Guest Street Extension
- All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 1/1/25. North side roadway improvements will coincide with adjacent development projects.
BUILDING A (Residential Building with new Stop & Shop Grocery Store)
- Alder residential building is occupied, and leasing is on-going. Retail leasing is on-going as well with no immediate retail construction anticipated for 2024. Stop and Shop opened June 21, 2024.
COMMUNITY GREEN
- Construction on the Community Green open space is on-going. Installation of walls, utilities, and curbing is substantially complete. Fencing and paver installation anticipated for December 2024 extending into early 2025. Remaining plantings and final telecommunications connections will be complete in Spring 2025 with Grand Opening scheduled for late spring/early summer 2025.
STOP & SHOP DEMOLITION
- Utility disconnects are occurring now in the rear of the store. Major demolition activities anticipated to begin 12/30 and extending through January. All demolition and site work anticipated to be complete February 2025.
For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906