INFRASTRUCTURE – new street grid: Guest Street extension, Arthur Street extension, Braintree Street extension, and improved Everett Street intersection)
Enabling – to pave the way for construction of future roadways
- Completing electrical infrastructure within future Braintree Street extension
- Making final connection to existing water infrastructure at intersection of Braintree Street and Old Everett Street
- Minor utility work in Everett Street
- Overall site cleanup and construction signage installation
Homegoods Demolition – to pave the way for construction of Building B
- Active building demolition on-going. Expected completion by mid-June
- Upon completion of active demolition, removal of material will continue for another week
Roadway Phase A – Everett Street intersection and Arthur Street extension improvements
- Everett Street intersection
- Sidewalk and roadway patching required for stormwater installation complete
- Test pitting in sidewalks and along edge of roadways to identify potential utility conflicts week of 5/30
- Arthur Street extension
- Completing tree removals and temporary sidewalk work week of 5/23
BUILDING B – Lab/Office Building
- Exploratory borings occurring week of 6/20
- Mobilization anticipated for 10/22
BUILDING A – Residential Building with new Stop & Shop grocery store
- Parking lot demolition, support of excavation and soil removal 100% complete
- Lower garage level (Level -2) concrete slab 75% complete
- Upper garage level (Level -1) concrete formwork has begun
- Concrete superstructure (2 underground + 2 above ground) forecast to complete Fall 2022
- Wood framing superstructure (Levels 3 to 6) forecast to complete Spring 2023
- Overall project completion forecast to complete Early 2024
For any questions, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906