INFRASTRUCTURE (Roadway and Utility Work)
Everett and Arthur Reconstructions
- Everett Street Intersection: All work substantially complete, with intersection fully activated. City accepted signals, finalizing acceptance of sidewalks.
- Arthur Street: All work substantially complete, with intersection fully activated. City accepted signals, finalizing acceptance of sidewalks.
Future Guest Street Extension
- All work substantially complete, with intersection fully activated. City currently reviewing documentation for acceptance of roadway. North side roadway improvements will coincide with adjacent development projects.
BUILDING A (Residential Building with new Stop & Shop Grocery Store)
- Alder residential building is occupied, and leasing is on-going. Retail leasing is on-going as well with no immediate retail construction planned. Stop and Shop opened June 21, 2024.
COMMUNITY GREEN
- Construction on the Community Green open space is on-going. Installation of walls, utilities, curbing, trees, and fencing is substantially complete. Paver installation has started and will continue through mid-May. Smaller plantings and surface treatments such as loam and stonedust are currently being installed to be completed by end of May. Telecommunications, lighting, and irrigation installation on-going to be completed by early June. Opening of the park planned for early-mid June.
STOP & SHOP DEMOLITION
- All demolition work is now complete.