Enabling – to pave the way for construction of future roadways
- Final utility connections
- Overall site cleanup and construction signage installation
Homegoods Demolition – to pave the way for construction of Building B
- All work complete and gravel pad being utilized by the Building A contractor for parking
Roadway Phase A – Everett Street intersection and Arthur Street extension improvements
- Everett Street intersection (Anticipated 2022 Work)
- Installing new retaining wall between Everett and Old Everett Streets.
- Pedestrian and bicyclist access to and from Stop & Shop via Everett Street closed-Fire department boxes installed. Pedestrian and bicyclist to detour to North Beacon and Arthur Street for Stop & Shop access.
- Installing stormwater infrastructure
- Preparing to install fire department conduit along east Everett Street sidewalk from Old Everett Street to North Beacon Street
- Relocating existing fire department call box
- Arthur Street extension
- Installing site lighting and traffic conduit
- Commencing landscaping work including bike lane and paver installation.
- Finishing curb installation
BUILDING A – Residential Building with new Stop & Shop grocery store
- Parking lot demolition, support of excavation and soil removal 100% complete
- Garage levels concrete installation complete
- Concrete superstructure (2-levels above grade) almost complete
- Wood framing superstructure (Levels 3 to 6) forecast to complete Spring 2023
- Overall project completion forecast to complete Early 2024
BUILDING B – Lab/Office Building
- Design and permitting on-going
- Mobilization anticipated for Spring 2023
For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906