October 21, 2024 – Construction Updates

INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 12/1/24.
  • Arthur Street: All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 12/1/24.

Future Guest Street Extension

  • All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 12/1/24. North side roadway improvements will coincide with adjacent development projects.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Final occupancy permit obtained. Residential tenant move in’s have begun and will continue to increase through the summer. Stop and Shop opened Friday, June 21st.

COMMUNITY GREEN

  • Construction on the Community Green open space has begun. Installation of walls, utilities, and hardscapes on-going, and anticipated to be complete by end of 2024. Landscaping and final telecommunications connections will be complete in Spring 2025 with Grand Opening scheduled for late spring/early summer 2025.

STOP & SHOP DEMOLITION 

  • Demolition of existing store is being permitted now. Utility disconnects anticipated to begin in early November with demolition commencement anticipated mid-late November 2024.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906