INFRASTRUCTURE (Roadway and Utility Work)
Everett and Arthur Reconstructions
- Everett Street Intersection: All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 10/1/24.
- Arthur Street: All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 10/1/24.
Future Guest Street Extension
- All work substantially complete, with intersection fully activated. Punch list work on-going to be completed by 10/1/24. North side roadway improvements will coincide with adjacent development projects.
BUILDING A (Residential Building with new Stop & Shop Grocery Store)
- Final occupancy permit obtained. Residential tenant move in’s have begun and will continue to increase through the summer. Stop and Shop opened Friday, June 21st.
COMMUNITY GREEN
- Construction on the Community Green open space has begun. Installation of walls, utilities, and hardscapes on-going, and anticipated to be complete by end of 2024. Landscaping and final telecommunications connections will be complete in Spring 2025 with Grand Opening scheduled for late spring/early summer 2025.
STOP & SHOP DEMOLITION
- Demolition of existing store is out for bid with contractors now. Permits and final design will proceed through September and early October with demolition commencement anticipated late Fall 2024.
For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906