INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of work complete for the season. Final paving, striping, and signal activation tentatively scheduled for May 2024.
  • Arthur Street: Majority of work complete for the season. Signal Activation tentatively scheduled for April 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete in March. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur immediately thereafter (late March). Gas line installation from Arthur Street to Building A expected to begin the week of February 20th and finishing in mid-late March.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work ongoing on south side of building. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing. Project substantial completion anticipated for Spring 2024.