INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of work complete for the season. Final paving, striping, and signal activation tentatively scheduled for May 2024.
  • Arthur Street: Majority of work complete for the season. Signal Activation tentatively scheduled for April 2024.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation ongoing and expected to be complete in March. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur immediately thereafter (late March). Gas line installation from Arthur Street to Building A has begun and is expected to be complete mid-late March.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work ongoing on south side of building. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing. Residential and base building substantial completion anticipated for Spring 2024 with Stop & Shop substantial completion anticipated for late spring/early summer.