INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Majority of work complete for the season. Final paving, striping, and signal activation to occur in the Spring.
  • Arthur Street: Majority of work complete for the season. Signal Activation to occur late Winter/early Spring.

Future Guest Street Extension

  • Sidewalks, bike lanes, and material installations have been completed. Paver installation to begin January 5th and extend through February. Remaining appurtenance installation such as benches, light poles, bike racks, landscaping etc. to occur early Spring. Gas line installation from Arthur Street to Building A expected to occur between early February to early March.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Exterior work ongoing on south side of building. Interior finishes, appliance installation, and HVAC improvements in levels 4-6 ongoing. Project completion anticipated for Spring 2024.