INFRASTRUCTURE – new street grid: Guest Street extension, Arthur Street extension, Braintree Street extension, and improved Everett Street intersection)

Enabling – to pave the way for construction of future roadways

  • Making final connection to existing water infrastructure at intersection of Braintree Street and Old Everett Street
  • Overall site cleanup and construction signage installation

Homegoods Demolition – to pave the way for construction of Building B

  • Active building demolition complete
  • Site clean-up ongoing
  • Stop & Shop building improvement and minor utility work happening in this area
  • Gravel pad to be utilized for Building A contractor parking

Roadway Phase A – Everett Street intersection and Arthur Street extension improvements

  • Everett Street intersection
    • Installing traffic management devices on Everett and Old Everett Streets restricting traffic to northbound only
    • Pedestrian and bicyclist access to and from Stop & Shop via Everett Street closed beginning July 27th until further notice. Stop & Shop to continue to remain open. Pedestrian and bicyclist to detour to North Beacon and Arthur Street for Stop & Shop access.
    • Installing stormwater structures/infrastructure
    • Demolishing and removing existing retaining wall
    • Installing foundation and precast retaining wall
  • Arthur Street extension
    • Installing site lighting and traffic conduit
    • Additional stormwater work at Hichborn intersection
    • Ordering and installing proposed curbing

BUILDING A – Residential Building with new Stop & Shop grocery store

  • Parking lot demolition, support of excavation and soil removal 100% complete
  • Lower garage level (Level -2) concrete slab 100% complete
  • Upper garage level (Level -1) concrete formwork ongoing
  • Concrete superstructure (2 underground + 2 above ground) forecast to complete Fall 2022
  • Wood framing superstructure (Levels 3 to 6) forecast to complete Spring 2023
  • Overall project completion forecast to complete Early 2024

BUILDING B – Lab/Office Building

  • Exploratory borings complete
  • Mobilization anticipated for 10/22