INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street Intersection: Signal activation occurred May 13th, final paving occurred June 3rd. Final striping of the intersection is scheduled for the week of 6/10. Two way traffic will be maintained during striping, however standard lane closures may impact traffic flow.
  • Arthur Street: All paving, striping and signal activation complete.

Future Guest Street Extension

  • Roadway and sidewalks were opened to public on May 13th, 2024. Majority of roadway and sidewalk work is complete. Minor punch list work remaining in sidewalk and paver areas. Installation of bike racks, benches, and trash receptacles to be complete week of June 10th. Final striping of the roadway is scheduled for the week of 6/10. Two way traffic will be maintained during striping, however standard lane closures may impact traffic flow.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Substantial completion has been achieved and an occupancy permit has been granted Minor work still on-going with an anticipated final completion by mid-summer. Residential tenant move in’s have begun and will continue to increase through the summer. Stop and Shop opening scheduled for Friday, June 21st.

COMMUNITY GREEN

    • Construction on the Community Green open space has begun. Early work consists of demolition, drainage installation, and earthwork. Plantings are scheduled for early fall of 2024 with an anticipated completion date by year end.