INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street:Majority of roadway work complete. Concrete patching in sidewalk occurring this week. Private utility (National Grid and Eversource) work will be occurring within Everett and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: Top course pavement scheduled for the night of Monday October 2nd. Activity this week will include work required for preparation of top course paving, including raising structures, installing message boards, and patching binder course pavement.

Future Guest Street Extension

  • Construction will commence in full of the hardscape area on the south side of Guest Street, including the bike lane, pavers, and sidewalk areas. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906