INFRASTRUCTURE (Roadway and Utility Work)

Everett and Arthur Reconstructions

  • Everett Street: Working on preparing roadway for final paving which is anticipated for mid-late October Preparation includes raising structures and preparing pavement transitions. Private utility (National Grid and Eversource) work is occurring within Everett and Braintree Streets, separate from the Allston Yards project.
  • Arthur Street: Top course pavement scheduled for the night of Friday, October 6th. Activity this week will include work required for preparation of top course paving, including raising structures, installing message boards, and patching binder course pavement.

Future Guest Street Extension

  • Construction of the hardscape area on the south side of Guest Street is progressing, including installation of the bike lane, pavers, and concrete sidewalks. Specific activities include installation of the structural soil (for trees), gravel base for bike lane, crushed stone base for pavers.

BUILDING A (Residential Building with new Stop & Shop Grocery Store)

  • Concrete and wood frame structural construction complete. Exterior building work ongoing including window, roof, and façade installation. Project completion (residential and retail) anticipated for Spring of 2024. Construction activities anticipated through that date.

For any questions regarding the updates above, please contact Dave Pellegri at dpellegri@nedevelopment.com or at 617-610-8906